Villa Lilly
Here are snapshots of building work, with the latest at top. Click on individual pictures if you want to see a bigger image.
2007-03-01
The outside heat insulation is done and the first coat too. The concrete part of the swimming pool is finished. Here you could see a part of the perimetre wall ,the retaining wall and the engine room. This is the septic tank.
2007-02-21
The heat insulation has been mounted.The UPVC windows have been mounted too. The perimetre wall and the retaining wall are in a process of building. The swimming pool is also in a process of building. An excavations for the septic tank are being done.
2007-01-30
The villa has already acquired a finished state.The roof has been done too.The supporting walls are in the process of building.The outside insullation is mounted.
2006-12-22
The first floor is alredy done and the second floor is in a process of building.
2006-12-02
The slab of the second floor has been cast.The foundations of the supporting walls have been done too.
2006-11-01
This is the beginning of the building process.The foundations of the villa have been done.
|